Design-Construction-Handover
Design
Mechanical:
PART 1 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- EQUIPMENT & ASSEMBLIES
"MECHANICAL DESIGNER TO COMPLETE THIS SHEET"
Ventilation:
PART 1 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- VENTILATION SYSTEM
"VENTILATION DESIGNER TO COMPLETE THIS SHEET"
Electrical:
PART 1 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- ELECTRICAL SYSTEM
"ELECTRICAL DESIGNER TO COMPLETE THIS SHEET"
Installation
Mechanical:
PART 2 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- EQUIPMENT & ASSEMBLIES
"MECHANICAL INSTALLER TO COMPLETE THIS SHEET"
Ventilation:
PART 2 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- VENTILATION SYSTEM
"VENTILATION INSTALLER TO COMPLETE THIS SHEET"
Electrical:
PART 2 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- ELECTRICAL SYSTEM
"ELECTRICAL INSTALLER TO COMPLETE THIS SHEET"
Inspection
Mechanical:
PART 3 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- EQUIPMENT & ASSEMBLIES
"MECHANICAL INSPECTOR TO COMPLETE THIS SHEET"
Ventilation:
PART 3 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- VENTILATION SYSTEM
"VENTILATION INSPECTOR TO COMPLETE THIS SHEET"
Electrical:
PART 3 of 3 - HAZARDOUS AREA COMPLETION CERTIFICATE- ELECTRICAL SYSTEM
"ELECTRICAL INSPECTOR TO COMPLETE THIS SHEET"
Client Handover
CLIENT ATEX HANDOVER CERTIFICATE
Following completion of a project, the installation should be taken in charge by the client .The attached handover sheet provides a formal mechanism for the handover of control of the installation to the client.
"CLIENT/EMPLOYER TO COMPLETE THIS SHEET"